RESIDENTS AND BUSINESSES OF KINGSWAY (BROCK ST. TO OAK ST.)

RESIDENTS AND BUSINESSES OF KINGSWAY (BROCK ST. TO OAK ST.)

2026 STREET RESURFACING PROGRAM

Milling existing asphalt: JULY 22, 2026
Paving new asphalt: JULY 31, 2026, weather permitting

We will:

  • Remove the worn top layer of asphalt by milling
  • Clean and prepare the roadway for paving
  • Adjust manholes and catch basins, where required
  • Pave a new asphalt surface and restore pavement markings
  • During construction:
  • Milling and paving may occur on different days
  • On-street parking will be temporarily restricted when No Parking signs are posted
  • Vehicle access to properties may be briefly interrupted as equipment passes
  • Pedestrian access to properties will be maintained
  • Regular garbage and recycling collection will not be affected
  • Please contact us if you have:
  • Accessibility needs
  • Access and delivery requirements
  • Planned special events
  • Questions about the project
  • You can reach us at 204-986-5018 or pwd-customer-service@winnipeg.ca