2019 Regional Sidewalk Renewal - Stafford Street

May 30, 2019

Starting the week of June 3, 2019, weather permitting, sidewalk renewal will be begin on the following streets: 

  • Stafford Street (east side) - Corydon Avenue to Mcmillan Avenue
  • Stafford Street (west side) - Yale Avenue to Corydon Avenue

The work will include removal of existing curb and sidewalk, construction of new concrete curb and sidewalk with paving stone banding, and installation of detectable warning tiles at intersections.

Work is expected to take approximatley two to three weeks, weather permitting. 

During construction, on-street parking will be prohibited and the curb lane will be barricaded at times.

Pedestrian access to all business and residential premises will be maintained.

Please contact Public Works with any accessibility needs or questions about the project at 204-226-2303. The contractor responsible for the sidewalk construction is J.C. Paving Ltd., who can be reached at 204-989-4700.